Mining Systems For Working Lode Deposits, Part I

Before opening a metal mine it is well to consider the following points. The nature and quantity of the material to be extracted; the general form of the deposit ; the depth at which you may have to work ; the nature of the boundaries (roof, floor, walls] the thickness of  the deposit ; its hardness and physical structure; the existence or  nonexistence of faults; the quantity of water which may be met with in the ground. To work economically, if possible arrange the works so that 'the underground transport shall be short, the slopes clear of water, and so that there shall be good ventilation, and the men not crowded. In ordinary lodes, half or three quarters of the men employed underground may be engaged in exploratory work (dead or head work.)

Working- Lodes of Ordinary Width.
Ordinary lodes which are from 2 feet to 6 feet wide, are worked either by overhand or underhand sloping. In Cornwall the price of stoping varies in cost depending on the width of the vein.

Overhand Stoping
It is better to commence from a winze than by breaking in. Tools and materials can be easily lowered down a winze, and the winze also acts as a passage for air. A fair height for a stope is 6 or 7 feet. A high face allows the material to come down in blocks, but the stage necessary for the workmen in such a case has to be removed before firing a shot. The length of a face may be from 20 to 40 feet. When the slopes are small the men may be inconveniently near to each other when a shot is fired. The workmen advance quickly if the joints in the rock dip towards them. A pass is formed by the walls, stemples and attle, or it may be timbered like a winze. The bottom of the pass ought to be larger than the top to prevent jamming. In a 90 feet pass the top may be 3 feet square and the bottom 4 feet 6 inches square. The limiting inclination is about 50. The advantages of overhand stoping are, I. The ground breaks readily. 2. The ore is thrown down a pass. 3. The water drains away. 4. The ventilation is good. 5. There is less timber employed as compared with underhand sloping, unless there are not enough dead ended workings to fill in with. The disadvantages are. I. The dead work of driving a level beneath the deposit. 2. The danger to the workmen. 3. The loss of ore amongst the attle. 4. The inconvenient position in which the men work.

 

 

Underhand Stoping
The floor and face of a stope ought to dip downwards. The height of the face may be 6 or 10 feet and the floor 25 to 40 feet. The advantages of this method are, I. The work may be commenced without previous dead work. 2. There is little risk of accident. 3. The workmen may use heavy double handed tools. 4. There is little loss of ore. The disadvantages are, I. The passing up of the ore. 2. The risk of water accumulating. 3. The quantity of timber required. 4. The difficulty of ventilation. These latter objections hardly apply if the usual system is followed of putting down a winze and bottom-stopping into it. Narrow widths- in working narrow veins a strip of the wall may be first removed and then the vein broken down unmixed with wall rock (stripping) otherwise they are worked by the ordinary methods of sloping.

Working Wide Lodes
Wide lodes are lodes where the material of the lode is too weak to stand as a roof without support.' Generally any lode over 8 or 10 feet will fall within this category. I. By Horizontal Slices. A level is driven along the footwall and at intervals of say 18 feet, levels or cross cuts are driven across the lode to the hanging wall. By driving these levels, a certain quantity of material is obtained from the lode. The cross cuts are then packed with attle, and a second set of new cross cuts are started inside the pillars: These being packed, a third set of cross cuts (each cross cut being 6 feet in width j will complete the extraction of a horizontal slice taken out transversely or across the lode from the footwall to the hanging wall. A second slice is then taken out at a higher level and so the work proceeds slice by slice working upwards. If it is not desirable to come in contact with the stowing, a thin slice of the vein may be left as a floor between two successive slices. When taking out slices in a descending order, the works in the upper slice should be in advance of those below. 2. By Vertical Slices. At Almaden in Spain, slices are taken vertically from level to level, the walls being supported by masonry. 3. Working by Pillars. This method is adopted where stowage is difficult to obtain. The slices, which are much thicker than in the previous method, are removed in descending order. Cross-cuts are driven from a main level in the hanging wall side, and possibly also another set of levels at right angles, so that a slice is divided up into a number of pillars. The pillars and portion of the roof are then cut away until the roof commences to fall, these operations commencing in the part of the mine furthest removed from the shaft. After this a second slice is commenced at a lower level, leaving a sufficiently strong roof between it and the crushed-in workings above. When working several slices simultaneously, the stripping of pillars, in a lower level must not be commenced until the upper level has been completely worked.

Examples of the cross-cut method with pillars are found at the Stahlberg Iron Mines, the calamine workings in Silesia, the alum shales at Liege etc. If the deposit is large, drive round it a horizontal contour level. This may be used as a main level from which cross cuts may be driven and the deposit worked out by the method of horizontal slices. The pillar method may also be employed. When material is extracted by a series of chambers the pillars of a lower tier are made larger than those of a tier at a higher level. At Musen near Siegen the vaults are i8ft. high and the pillars between are 1 2ft. thick. Only one-third of the material (iron carbonate) is obtained from each level.

 

 

Post and Stull Method.  
Usually a shaft is sunk on the deepest side (dip side) of the area to be worked, in a central position on that side. Two or more levels (say 10 feet wide) are driven parallel to the strike (dip head level, lodgment level or water way) slightly inclined towards the shaft. The lower of these is used to convey water to the sump, while the others are employed for haulage or as a level from which the stulls or boards are laid out when working (winning) the coal. These are usually laid out, so that they advance in a direction at right angles to the cleat or cleavage, such a direction being known as " on the face or board ways" The direction at right .angles to this is known as " on the ends." Occasionally circumstances (as for example a steep dip) demand that the boards shall advance obliquely to the cleat or even parallel to it, that is on the ends. When there is only one direction of cleat, the coal has a tendency to break into prismatic forms. If there are two sets of cleavage at right angles (backs and cutters) the coal will be cuboidal if oblique, rhomboidal &c If advancing at right angles to well defined backs, the coal will come away with ease, but in consequence of the under-Cutting and falling, so many additional fissures may be produced, that two much stnaffs or dust coal may be produced. In such a case, advance the boards in some direction oblique to the backs or even on end.

The winning headway from which boards are driven may therefore be parallel to the strike, the dip, or in some intermediate direction. At least two board ways which are as wide as the roof will stand without support (10 to 15 feet) are driven together. After advancing a certain distance the working faces are joined by a passage or thirling, parallel to the winning headway. The boards are then advanced, a second thirling driven and the first thirling may be temporarily stopped. The ventilating current now passes round the working faces through the second thirling. By a system of boards and thirlings at right angles to each other the area to be worked, is cut up into a series of pillars. If these pillars are made too small they become crushed and cannot be subsequently removed, and more than half of the whole seam may be destroyed.

Continue on to:
Quartz Lode Mining Systems, Part II, Shafts
 

Return To:
Hard Rock Quartz Mining and Milling

 

.

Nevada Outback Gems

Find out more by checking out All of our links below:

http://nevada-outback-gems.com/Rough_n_crystal/ebay_logo3.jpg

View our Contemporary Turquoise Jewelry - Wearable Artwork! View our Unique Gem Quality Turquoise Cabochons
Premium Jewelry, with Gemstones of all types Top Quality Loose Gemstones - Gemstones of all types
Rare Crystals and Gemstone Rough, all types Our Free Colored Gemstone Information Encyclopedia
Chris' Gold Prospecting Encyclopedia Take a virtual tour of our Nevada Turquoise mines
Miners Reference Pages         More Info about Turquoise, the Beautiful Gem
Basic Placer Mining Mineral Photo Gallery Nevada Outback Gems Homepage
Build Your Own Mining Equipment Investing in Gold and Precious Metals
Metal Detecting with the MXT Metal Detector More information about us - Nevada Outback Gems
Locations to Prospect for Gold The Rockhound's Corner Nevada Outback Library and Bookstore - Learn more!
  Chris's Prospecting Adventures About Nevada Turquoise More Info about Gem Cutting Tanzanite Jewelry
Nevada Outback Gems Site Map Make Your Own Jewelry Photos of Precious Metal Ores